Project progress

Last update: (11/06/2015)

 

The following tables how information about the project progress. The first table shows the status of the project milestones. This page will be updated twice a year.

IDMilestoneActionDateCurrent statusComments
M1 Documentation of the model beyond Virtual Crop B1 23/03/2013 Achieved
  • Documentation about Virtual Crop defined
M2 Start Demonstration of IES in experimental Plots B5 01/04/2013 Achieved
  • Setup finished
  • Irrigation strategies started
  • Collection data for validation
M3 Start Monitoring of farmers practices B5 01/04/2013 Achieved
  • Flowmeters installed
  • Colecting data for validation
M4 Irrigation Virtual module prototype B2 28/06/2013 Achieved
  • Functionalities and requirements defined
  • Use cases defined
  • Prototype implementation finished
M5 Final platform B3 31/01/2014 Achieved
  • Development finished
  • IES platform avaiable on www.ies-sim.com
M6 Start Web Analytics B5 03/02/2014 Achieved
  • Web analytics configured 
M7 Positive project progress at mid-term E1 18/06/2014 Achieved
  • Project progress evaluation finished
M8 Start Projection of IES at regional level B5 04/08/2014 Achieved
  • Starting batch development  
  • Starting face to face trainings
M9 Report on progress of communication plan D1 23/10/2014 Achieved
  • Face to face trainings
  • Presence in regional fairs
  • International congresses
  • Leaflets and roller 
M10 End Demonstration of IES in experimental Plots B5 31/10/2014 OnGoing
  • Studying data from 2013 and 2014 
  • Data acquisition from the experimantal plot will continue during 2015 
M11 Report on progress of training plan D1 21/01/2015 Achieved
  • 8 face to face trainings
  • 87 students 
M12 Report on IES potential impact at regional scale B5 18/03/2015 Achieved
  • Executed simulations over 200 different plots and 9 different irrigation strategies
  • More than 5000 simulations executed 
M13 Report on the progress on indicators C1 27/05/2015 OnGoing
  • Good progress on indicators 
M14 End Projection of IES at regional level B5 30/06/2015 OnGoing
  • Finishing face to face trainings
  • Boosting online trainings 
M15 End Web Analytics B5 18/09/2015 Upcoming  
M16 End Monitoring of farmers practices B5 18/09/2015 Achieved
  • Data from farmer's plots only collected during 2013 and 2014. 
M17 Positive final technical and financial reports E1 14/10/2015 Upcoming  

 

This table shows the finished deliverables:

 

IDDeliverableActionFinishing date
D1.1 Communication Plan D1 04/12/2012
D1.2 Project web site D1 13/12/2012
B1.1 Review of irrigation scheduling strategies B1 15/12/2012
B2.1 Irrigator Scheduler Prototype B2 22/12/2012
B1.2 Documentation of the Irrigator Scheduler B1 25/01/2013
B2.2 Virtual Crop prototype B2 22/02/2013
B3.1 List of reports B3 15/03/2013
B1.3 Documentation of the model beyound Virtual Crop B1 22/03/2013
B3.2 Comparative water savings model template B3 14/04/2013
B2.3 Irrigation Expert System prototype B2 24/04/2013
B3.3 Irrigation scheduler simulator model template B3 29/04/2013
B3.4 Virtual Crop model template B3 29/04/2013
B4.1 Report describing tables of reference data feed B4 29/05/2013
B3.6 Virtual results interface B3 28/06/2013
B2.4 Irrigation Virtual module prototype B2 28/06/2013
B5.2 Deployment of the survey in farmers' plots B5 11/07/2013
B5.1 Setup of the pilot plots B5 11/07/2013
B3.7 Recommendation structures B3 23/09/2013
C1.1 Report from the baseline, specific indicators C1 20/10/2013
B3.8 Web based application B3 20/11/2013
B4.2 Report describing reference data to specific scenarios B4 30/11/2013
B3.9 Portal prototype B3 20/12/2013
C1.2 Report on the progres of indicator C1 29/01/2014
B5.3 IES web analytics B5 31/01/2014
B3.10 Final platform B3 31/01/2014
B5.4 Results of the pilot plots during the first year B5 12/03/2014
B4.3 Report describing production losses B4 11/04/2014
D1.4 Training plan D1 14/05/2014
E1.1 Positive project progress at mid-term E1 18/06/2014
B5.5 Report on IES potential impact at regional scale B5 28/03/2015
C1.3 Report on the socioeconomic impact of the project C1 18/05/2015